1. | A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is : |
|
(A + B)'s 1 day's work = | | 1 | + | 1 | | = | 7 | . |
15 | 20 | 60 |
(A + B)'s 4 day's work = | | 7 | x 4 | | = | 7 | . |
60 | 15 |
Therefore, Remaining work = | | 1 - | 7 | | = | 8 | . |
15 | 15 |
2. | A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
|
(A + B + C)'s 1 day's work = | 1 | , |
4 |
C's 1 day's work = | 1 | - | | 1 | + | 1 | | = | | 1 | - | 7 | | = | 5 | . |
4 | 16 | 12 | 4 | 48 | 48 |
So, C alone can do the work in | 48 | = 9 | 3 | days. |
5 | 5 |
3. | A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day? |
A's 2 day's work = | | 1 | x 2 | | = | 1 | . |
20 | 10 |
(A + B + C)'s 1 day's work = | | 1 | + | 1 | + | 1 | | = | 6 | = | 1 | . |
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | | 1 | + | 1 | | = | 1 | . |
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
4. | A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
|
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
If difference of time is 60 days, B takes | | 3 | x 60 | | = 90 days. |
2 |
So, A takes 30 days to do the work.
(A + B)'s 1 day's work = | | 1 | + | 1 | | = | 4 | = | 2 |
30 | 90 | 90 | 45 |
A and B together can do the work in | 45 | = 22 | 1 | days. |
2 | 2 |
5. |
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C? |
C's 1 day's work = | 1 | - | | 1 | + | 1 | | = | 1 | - | 7 | = | 1 | . |
3 | 6 | 8 | 3 | 24 | 24 |
A's wages : B's wages : C's wages = | 1 | : | 1 | : | 1 | = 4 : 3 : 1. |
6 | 8 | 24 |
C's share (for 3 days) = Rs. | | 3 x | 1 | x 3200 | | = Rs. 400. |
24 |
6. | If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be: |
Let 1 man's 1 day's work = x and 1 boy's 1 day's work = y.
Then, 6x + 8y = | 1 | and 26x + 48y = | 1 | . |
10 | 2 |
Solving these two equations, we get : x = | 1 | and y = | 1 | . |
100 | 200 |
(15 men + 20 boy)'s 1 day's work = | | 15 | + | 20 | | = | 1 | . |
100 | 200 | 4 |
15 men and 20 boys can do the work in 4 days.
7. | A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
|
(B + C)'s 1 hour's work = | 1 | ; |
3 |
(A + C)'s 1 hour's work = | 1 | . |
2 |
(A + B + C)'s 1 hour's work = | | 1 | + | 1 | | = | 7 | . |
4 | 3 | 12 |
B's 1 hour's work = | | 7 | - | 1 | | = | 1 | . |
12 | 2 | 12 |
B alone will take 12 hours to do the work.
8. | A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in: |
(A + B)'s 1 day's work = | 1 |
10 |
(A + B + C)'s 1 day's work = | | 1 | + | 1 | | = | 6 | = | 3 | . .... (i) |
10 | 50 | 50 | 25 |
A's 1 day's work = (B + C)'s 1 day's work .... (ii)
From (i) and (ii), we get: 2 x (A's 1 day's work) = | 3 |
25 |
A's 1 day's work = | 3 | . |
50 |
B's 1 day's work | | 1 | - | 3 | | = | 2 | = | 1 | . |
10 | 50 | 50 | 25 |
So, B alone could do the work in 25 days.
9. | A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
|
Whole work is done by A in | | 20 x | 5 | | = 25 days. |
4 |
Now, | | 1 - | 4 | | i.e., | 1 | work is done by A and B in 3 days. |
5 | 5 |
Whole work will be done by A and B in (3 x 5) = 15 days.
A's 1 day's work = | 1 | , (A + B)'s 1 day's work = | 1 | . |
25 | 15 |
B's 1 day's work = | | 1 | - | 1 | | = | 4 | = | 2 | . |
15 | 25 | 150 | 75 |
So, B alone would do the work in | 75 | = 37 | 1 | days. |
2 | 2 |
10. | A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?
|
(P + Q + R)'s 1 hour's work = | | 1 | + | 1 | + | 1 | | = | 37 | . |
8 | 10 | 12 | 120 |
Work done by P, Q and R in 2 hours = | | 37 | x 2 | | = | 37 | . |
120 | 60 |
Remaining work = | | 1 - | 37 | | = | 23 | . |
60 | 60 |
(Q + R)'s 1 hour's work = | | 1 | + | 1 | | = | 11 | . |
10 | 12 | 60 |
Now, | 11 | work is done by Q and R in 1 hour. |
60 |
So, | 23 | work will be done by Q and R in | | 60 | x | 23 | | = | 23 | hours 2 hours. |
60 | 11 | 60 | 11 |
So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.
11. | A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
|
B's 10 day's work = | | 1 | x 10 | | = | 2 | . |
15 | 3 |
Remaining work = | | 1 - | 2 | | = | 1 | . |
3 | 3 |
Now, | 1 | work is done by A in 1 day. |
18 |
| 1 | work is done by A in | | 18 x | 1 | | = 6 days. |
3 | 3 |
12. | 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it? |
Let 1 man's 1 day's work = x and 1 woman's 1 day's work = y.
Then, 4x + 6y = | 1 | and 3x + 7y = | 1 | . |
8 | 10 |
Solving the two equations, we get: x = | 11 | , y = | 1 |
400 | 400 |
1 woman's 1 day's work = | 1 | . |
400 |
10 women's 1 day's work = | | 1 | x 10 | | = | 1 | . |
400 | 40 |
Hence, 10 women will complete the work in 40 days.
13. | A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?
|
(A + B)'s 20 day's work = | | 1 | x 20 | | = | 2 | . |
30 | 3 |
Remaining work = | | 1 - | 2 | | = | 1 | . |
3 | 3 |
Now, | 1 | work is done by A in 20 days. |
3 |
Therefore, the whole work will be done by A in (20 x 3) = 60 days.
14. | P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
|
P can complete the work in (12 x 8) hrs. = 96 hrs.
Q can complete the work in (8 x 10) hrs. = 80 hrs.
P's1 hour's work = | 1 | and Q's 1 hour's work = | 1 | . |
96 | 80 |
(P + Q)'s 1 hour's work = | | 1 | + | 1 | | = | 11 | . |
96 | 80 | 480 |
So, both P and Q will finish the work in | | 480 | | hrs. |
11 |
Number of days of 8 hours each = | | 480 | x | 1 | | = | 60 | days = 5 | 5 | days. |
11 | 8 | 11 | 11 |
15. | 10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?
|
1 woman's 1 day's work = | 1 |
70 |
1 child's 1 day's work = | 1 |
140 |
(5 women + 10 children)'s day's work = | | 5 | + | 10 | | = | | 1 | + | 1 | | = | 1 |
70 | 140 | 14 | 14 | 7 |
5 women and 10 children will complete the work in 7 days.
No comments:
Post a Comment